Building the Faith
Building The Faith
page 1
page 2
Original Sanctuary
Educational Wing
Replace Sanctuary
Introduction |

Composite Building Outline
Showing each of the three phases
This shows each of the three phases and how they fit together. State Route 31 runs along the bottom of the diagram, with Trenton to the right (as we look at the figure) and Flemington to the left.
Phase 1: 1968
4,138 square foot
no basement
poured slab floor
Phase 2: 1976
3,536 square foot
no basement
poured slab floor
Phase 3: 2000
4,178 square foot First Floor
3,515 square foot Basement
poured slab basement floor
   |